July 1, 2007 - June 30, 2008
Updated 7/17/07
|
Program |
Action Plan / Goal |
Status |
|
ADM Adminstration |
Complete all identified administrative
requirements by June 30, 2008 |
|
|
ADM Annual Meeting |
Hold Annual Meeting by February 28, 2008 |
|
|
ADM Budgeting |
Use local budget law process to develop and adopt
budget for FY 08-09 prior to June 30, 2008 |
|
|
ADM District Capacity |
Complete at least 3 actions to improve the
capabilities of this and other OR SWCDs by June 2008 |
|
|
ADM Safety |
Maintain high level of safety awareness and
remain accident free during the entire year. |
|
|
GEN Ag
Sustainability |
Provide at least 4 opportunities for farmers and
ranchers to learn about methods to improve soil quality by June 08. |
|
|
GEN Backyard Conservation |
Conduct a backyard xeriscaping workshop by
10/30/07 |
|
|
GEN CAFO |
Assist private landowners in complying with State
confined animal feeding operations regulations. |
|
|
GEN Conservation Equipment |
Make mower and mulcher available to area
producers during the year |
|
|
GEN CRMP |
Make use of Coordinated Resource Management
Planning (CRMP) process in |
|
|
GEN District Cost Share Pgm |
Implement District Cost Share Program with at
least 12 projects by June 2008 |
|
|
GEN Dry Crk Habitat Restor. |
By June 30, 2008 make all preparations necessary
to install instream habitat structures on Dry Creek. |
|
|
GEN Dry Crk Erosion Control |
By Dec 30, 2007 install 10 water & sediment
control basins in Dry Creek Watershed. |
|
|
GEN Farm Bill Support |
Implement 2002 Farm Bill Programs, by promotion,
technical assistance, and reporting through June 2008 |
|
|
GEN Horsekeeping Workshop |
Hold horse keeping workshop by September 30,
2007. |
|
|
GEN Irrigation Ditches |
Provide assistance to Irrigation Districts in the
|
|
|
GEN Mosier Groundwater Study |
Complete Mosier Groundwater model development and
analysis by 4/30/08 |
|
|
GEN Monitoring, multi-project |
Complete Annual Monitoring Requirements for
Previously Completed Projects |
|
|
GEN N. Fork Mill Crk Culvert |
Replace N.Fork Mill Creek culvert with bottomless
arch culvert for fish passage by October 30, 2007 |
|
|
GEN No Till |
By 12/30/07 complete direct seed conversions on
600 ac. under the |
|
|
GEN Nursery |
Complete one new demonstration at H.A. Miller
Demonstration Nursery by June 2008 |
|
|
GEN Pig Control Project |
Support feral pig control project with south |
|
|
GEN Fifteenmile Riverkeeper |
By November 30, 2007 complete Riverkeeper project
on upper Fifteenmile. |
|
|
GEN Rock Creek Piping design |
Complete Rock Creek Ditch piping system design
project by 11/1/07 |
|
|
GEN Roof Water Harvesting Demo |
Complete preparations for installation of
demonstration Roof Water harvesting system by June 30, 2008 |
|
|
GEN Small Grant Program |
|
|
|
GEN Steelhead-15mi Monitoring |
Develop Comprehensive Steelhead and Water Quality
Monitoring Program for Fifteenmile watershed by June 2008. |
|
|
GEN Streambank treatment |
Prepare for installation of streambank protection
measures on lower Fifteenmile Creek at two sites by June 2008 |
|
|
GEN Stump Grinding Demo |
Implement Stump Grinding Demonstration by June
2008 |
|
|
GEN Tech Dryland Chem Reduc. |
Implement Dryland Chemical Reduction Technologies
by June 2008 |
|
|
GEN Tech Precision Ag Dryland |
Implement dryland precision ag technologies (GPS
for overlap avoidance; selective spray) on by June 2008 |
|
|
GEN Tech Precision Ag Orchards |
Implement Orchard Precision Ag Chemical Reduction
Technologies by June 2008 |
|
|
GEN Plant Materials |
Get at least 50,000 Conservation Trees and Shrubs
planted by May 1, 2008 |
|
|
|
Install Bridge at Turner Ranch on Eightmile Creek
by November 1, 2007 |
|
|
GEN Weather Station Drift Reduc |
Secure funds for weather stations in |
|
|
GEN Wildlife Habitat Imp. - CRP |
Initiate program to assist |
|
|
GEN WYEAST RC&D Support |
Provide organizational support to WyEast RC&D
Area Council through June 2008 |
|
|
IEM Conservation Awards |
By November 3, 2007 submit at least 7 nominations
for the |
|
|
IEM Marketing |
By June 30, 2008, publish at least twelve
articles on the SWCD and its accomplishments in |
|
|
IEM Newsletter |
Distribute at least six bi-monthly issues of
Groundwork by June 2008 |
r |
|
IEM Public Information |
Participate in at least 36 public information
activities by June 2008 |
|
|
IEM Rural Living Handbook |
By June 2008 Develop, Print and Distribute at
least 2,000 Wasco County Rural Living Handbooks |
|
|
ORP CREP buffers (CP) |
Establish 10 riparian buffers in Lower
Deschutes/John Day subbasins by May 08 |
|
|
ORP CREP buffers (15) |
Establish 12 riparian buffers in Fifteenmile / Gorge Province by June
2008. |
|
|
ORP CREP buffers (ODA) |
Complete ODA CREP Technical Assistance
Requirments by June 2008. |
|
|
ORP Tech Assist Contacts |
Make 300 landowner/operator contacts by June 15,
2008 |
|
|
ORP Tech Assist Plans |
Write 34 new individual conservation plans / plan
revisions by June 15, 2008 |
|
|
ORP Tech Assist Practices |
Provide Technical Assistance implementing 40
practices benefiting water quality by June 2008 |
|
|
ORP
Water Quality (LMA) |
Implement |
|
|
WSP
Bakeoven Watershed |
Implement Bakeoven Watershed Action Plan through
June 2008 |
|
|
WSP Buck Hollow Monitoring |
Conduct annual monitoring in Buck Hollow
Watershed Project by June 2008 |
|
|
WSP Fifteenmile Watershed |
Implement the Fifteenmile Watershed Council
Action Plan through June 2008 |
|
|
WSP Mosier Watershed |
Implement the Mosier Watershed Action Plan
through June 2008 |
|
|
WSP Pine Hollow Watershed |
Assist |
|
|
WSP The Dalles Watershed |
Implement |
|
|
|
|
|
Each Goal pertains to an action plan which may have 6 or 60 individual tasks or actions